Budgeted Cost of Work Performed (BCWP)

Budgeted Cost of Work Performed (BCWP) is a term used in project management to describe the actual value of the work that has been completed on a project at a given point in time. BCWP is an important metric for measuring project progress and performance.

BCWP is calculated by multiplying the percentage of work completed by the total budget for the project. This gives the amount of budgeted cost of work that was planned to be completed by the given point in time.

BCWP can be compared to the budgeted cost of work scheduled (BCWS) and the actual cost of work performed (ACWP) to provide a comprehensive picture of project performance. By comparing these values, project managers can determine if a project is on schedule, under budget, or over budget.

BCWP is an important tool for project managers because it helps them to stay on track and identify potential issues before they become major problems. By tracking BCWP over time, project managers can make adjustments to the project plan to keep it on schedule and within budget.


Budgeted Cost of Work Performed (BCWP) Vs. Actual Cost of Work Performed (ACWP)

Budgeted Cost of Work Performed (BCWP) is a measure used in project management that shows the amount of the project budget that has been earned by completing the work that has been scheduled. On the other hand, Actual Cost of Work Performed (ACWP) represents the actual costs incurred in completing the work that has been scheduled.

BCWP is also known as the "earned value" of the project, as it represents the value of the work completed at any given point in time, based on the project schedule. In contrast, ACWP is the actual cost incurred to complete the work, regardless of the scheduled value of the work.

By comparing BCWP and ACWP, project managers can determine whether they are completing work on time and on budget. If BCWP is higher than ACWP, it means the project is ahead of schedule and under budget. If ACWP is higher than BCWP, it means the project is behind schedule and over budget.

In summary, BCWP represents the planned value of the work that has been completed, while ACWP represents the actual cost of the work that has been completed. By comparing these two values, project managers can gain insight into the project's performance and adjust their plans accordingly.


Steps to Calculate Budgeted Cost of Work Performed (BCWP)

The following are the steps to calculate Budgeted Cost of Work Performed (BCWP):

  • Determine the budgeted cost for each activity: The first step is to determine the budgeted cost for each activity or task in the project plan. This involves breaking down the project into individual tasks and assigning a budgeted cost to each task.
  • Determine the percentage of completion for each activity: The next step is to determine the percentage of completion for each activity or task. This involves tracking the progress of each task and determining how much of the work has been completed.
  • Calculate the earned value for each activity: The earned value is the value of the work that has been completed based on the percentage of completion. To calculate the earned value, multiply the budgeted cost of the activity by the percentage of completion.
  • Add up the earned values for all completed activities: Once you have calculated the earned value for each completed activity, add them up to get the total budgeted cost of work performed (BCWP) for the project.
  • Compare BCWP to actual cost of work performed (ACWP): Finally, compare the budgeted cost of work performed (BCWP) to the actual cost of work performed (ACWP) to determine whether the project is on track or over budget.


Reporting Budgeted Cost of Work Performed (BCWP)

Budgeted Cost of Work Performed (BCWP) is reported in various ways depending on the specific project management methodology being used. In general, it is reported as a key performance indicator (KPI) and included in regular status reports or progress reports. It is also often included in earned value management (EVM) reports and dashboards, which provide a comprehensive overview of project performance. In addition, BCWP may be used to generate cost performance index (CPI) and schedule performance index (SPI) metrics, which are important indicators of project health and progress.


Benefits and Drawbacks of Budgeted Cost of Work Performed (BCWP)

Benefits:

  • Helps in assessing project performance and identifying potential problems early on.
  • Provides an objective measure of progress toward project goals and objectives.
  • Helps in making informed decisions about project cost, time and resources.
  • Facilitates effective communication with project stakeholders by providing a common language and understanding of project performance.

Drawbacks:

  • It requires a significant amount of effort and resources to collect, organize, and analyze project data.
  • It assumes that the budget and schedule are accurate and realistic, which may not always be the case.
  • It is a backward-looking measure that does not provide insight into future project performance.
  • It can be easily manipulated if the project team is incentivized to show positive results.